The Challenges Faced by Private Project Developers in Securing Financing for Hydropower Projects in Zambia
Abstract:
The study investigated the challenges faced by private
project developers in securing financing for hydropower projects in Zambia. It was
a cross sectional exploratory study based on the pragmatic research philosophy.
The multiple case study research strategy was utilized in the study. Mixed methods
were selected as research choice and non-probabilistic was used as the sampling
technique. Primary data was collected through semi-structured interviews and secondary
data was obtained from library and internet. The population of the study comprised
13 hydropower projects that were being promoted by the Office for Promoting Private
Power Investment.
Five of Thirteen (38.5%) hydropower projects were considered
for the study having relevant data for the study. Purposive sampling was used to
select the projects. Quantitative and qualitative data was collected and analysed.
The study found that the challenges in securing financing for hydropower
projects in Zambia were related to the non-fulfillment of the key conditions required
for nonrecourse financing of hydropower projects. Those conditions were
1.
Development Mode of the project
2.
Sharing of project unlimited
risks
3.
Government guarantees for
project credit enhancement
4.
The Level of electricity
tariffs
5.
The Power off-taker for the
project and
6.
Provision of escrow arrangements
by the off-taker.
The study concluded that the efforts made by Government to support private
investment in hydropower projects did not directly address the risks associated
with project finance mobilisation. It was therefore recommended that Government
addresses these requirements from the lenders and developers in line with the principles
of project finance to enable the hydropower projects secure financing in Zambia.
Keywords: Project Mode, Unlimited
Risks, Government Guarantee, Electricity Tariffs, Off-Taker, Escrow, Project Financing.
References:
[1]. African Development Bank (2011) Independent Review Mechanism on The Implementation of Findings Of
Non-Compliance And Related Actions to Be Undertaken By The AFDB Management on For
The Bujagali Hydropower And Interconnection Projects of June, 2011; Bujagali; AFDB.
[2].
Central Statistics Office (2012), The Living Conditions Monitoring Survey Report
2006 & 2010, Lusaka: Living Conditions Monitoring Branch, CSO.
[3].
Chapman, C. and Ward, S. (2003) Project Risk Management: Processes, Techniques
and Insights 2nd edition, Chichester: John Wiley & Sons ltd.
[4].
Electricity
Act Chapter 433 of the Laws of Zambia (1995) Lusaka, GRZ.
[5].
Energy Regulation
Act Chapter 436 of the Laws of Zambia (1995), Lusaka, GRZ.
[6].
Fight, A. (2006) Introduction to Project Finance, Oxford: Butterworth-Heinemann.
[7].
Finnerty, J. D. (2007) Project Financing; Asset-Based Financial Engineering
[pdf], New York: John Wiley & Sons Inc. https://www.academia.edu/23726748/Project_Financing_Asset_Finnerty.
[8].
Head C. (2000) Financing of Private Hydropower Projects, Washington DC; No.WPD420;
The International Bank for Reconstruction and Development/The World Bank.
[9].
Japan International Cooperation Agency Value
Planning International, Inc. (March 2011) Case
Studies in Capacity Development in Power Sector with South-South Cooperation Components
Final Report, The New Cornerstone for Capacity-Building Programs held in March,
2011 in Washington, U.S.A.
[10]. http://www.jica.go.jp/usa/english/office/others/pdf/publication_110527.pdf.
[11]. Kahn, R.
and Cannell, C. (1957) The Dynamics of Interviewing. New York and Chichester:
Wiley.
[12]. Kalitsi
E.A.K (2003) Problems and Prospects For Hydropower
Development In Africa; The Workshop for African Energy Experts on Operationalizing
the NGPAD Energy Initiative 2 – 4 June 2003 Novotel, Dakar, Senegal; viewed 28 February
2014; http://sustainabledevelopment.un.org/content/documents/nepadkalitsi.pdf.
[13]. Kothari,
C. R. (2012) Research Methodology: Methods
and Techniques 3rd edition, New Delhi: New Age International Publishers.
[14]. Kumar, R.
(2011) Research Methodology: A step by Step
Guide for Beginners, London: SAGE Publication.
[15]. Lester,
A. (2007) Project Planning and Control 5th
edition, London: Elsevier.
[16]. Marczyk,
G., DeMatteo, D., Festinger, D. (2005) Essentials
of Research Design and Methodology, New Jersey: John Wiley & Sons Inc.
[17]. MEWD/OPPPI/103/5/1; Closed
Volume, Date- 30 May 2011 to 17 June 2013.
[18]. MEWD/OPPPI/103/5/17; Closed
Volume, Date- 30 November 2005 to 16 December 2008.
[19]. MEWD/OPPPI/103/5/3; Closed
Volume, Date- 1 August 2003 to 7 August 2013.
[20]. MEWD/OPPPI/103/5/30; Closed
Volume, Date- 13 June 2011 to 19 September 2013.
[21]. Ministry
of Energy and Water Development (2008) Rural
Electrification Master Plan, Lusaka: JICA & MEWD.
[22]. Ministry
of Energy and Water Development (1998) Framework
and Package of Incentives for Private Sector Participation in Hydropower Generation
and Transmission, Lusaka: MEWD.
[23]. Ministry
of Energy and Water Development (2008) National
Energy Policy, Lusaka: MEWD.
[24]. Ministry
of Energy and Water Development (2010) The
Study for Power System Development Master Plan in Zambia Final Report: Lusaka,
JICA & MEWD.
[25]. Ministry
of Finance and National Planning (2011) Sixth
National Development Plan (SNDP) 2011-2015, Lusaka, MFNP.
[26]. MMEWD/OPPPI/101/10/15; Date-
12 September 2011 to 2 May 2014.
[27]. MMEWD/OPPPI/101/10/2; Date-
29 August 2006 to 5 May 2014.
[28]. MMEWD/OPPPI/101/10/3; Date-
09 October 2013 to 19 March 2014.
[29]. MMEWD/OPPPI/101/10/5; Date-
19 September 2013 to 31 March 2014.
[30]. MMEWD/OPPPI/101/10/6; Date-
30 December 2008 to 15 April 2014.
[31]. MMEWD/OPPPI/101/10/8; Date-
7 August 2013 to 30 April 2014.
[32]. Nag, P.
K., (2008), Power Plant Engineering, 3rd
edition, New Delhi: Tata McGraw-Hill.
[33]. Norwegian
Tunnelling Society (2012) Contracts in Norwegian
tunnelling; Publication No. 21, Oslo, NFF.
[34]. Meki Wallce
(2014) An Investigation on Hindrances Faced by Private Project Developers in Securing
Debt for Hydropower Projects, Unpublished
Dissertation, Lusaka, CUZ.
[35]. Rabin, M.
(2007) What Are the Geological and Hydrological
Risks and Issues Affecting Hydropower Financing? University of Dundee, viewed
19 November 2013; http://www.dundee.ac.uk/cepmlp/gateway/files.php%3Ffile%3DCAR-11_12_476864027.pdf.
[36]. Saunders,
M., Lewis, P., Thornhill, A. (2016) Research
Methods for Business Students 7th edition, Harlow: Pearson Education Ltd.
[37]. Sexana,
P. and Kumar, A. (2010) Hydropower Development
in India, Ighem-2010, Oct. 21-23, 2010, AHEC, IIT Roorkee, India; viewed 2 January
2014;http://ighem.org/Paper2010/TSA01.pdf.
[38]. Singh, Y.
K. (2006) Fundamentals of Research Methodology
and Statistics, New Delhi: New Age International Publishers.
[39]. Spiegl,
M and Schneider, E. (2002,) Dealing with Geological
Risk in BOT-Contracts: Proposal for a
supplementary module to BOT-contracts under International Competitive Bidding (ICB),
United Engineering Foundation – UEF 15.-19. Sept. Graz, Austria.
[40]. The Infrastructure
Consortium for Africa (2011) WHEN POWER COMES-
An analysis of IPPs in Africa, Tunis; African Development bank; viewed 28 February
2014; http://www.icafrica.org.
[41]. U.S. Agency
for International Development (2008) ELECTRICITY
SUPPLY INDUSTRY IN ZAMBIA; General Information for Potential Investors, Washington
DC, USAID.
[42]. Verzuh,
E. (2003) The Portable MBA in Project Management,
New Jersey: John Wiley & Sons Inc.
[43]. Yin, R.K.
(2003) Case Study Research: Design and Method 3rd edition. London:
Sage.
[44]. Zambia Development
Agency (January 2014) Public-Private-Partnerships
in Infrastructure Development in Zambia; ZDA, Lusaka.
[45]. Zambia Development
Agency (2013) Zambia Energy Sector Profile;
Lusaka, ZDA.
[46]. ZESCO (2014)
Power Rehabilitation Program; viewed on
22 April 2014; http://www.zesco.co.zm/CAAndBD/Projects/ZescoGenerationCapacityUpto2015.html.